customized simulation in navis works


sreejithu

Recommended Posts

While simulating a project in 4D, Navisworks shows 0% (task start), and 100% (end of task) in the model. What do i do if i want to visualise 50% (part completion) of a task o be shown in the model.

Pn- Schedule to Be attached in MSP

 

For eg- activity X takes 5 days to complete, can navis works represent part completion( say 20%, 40%) as it simulates from day 1 to day 5

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Unfortunately, your content contains terms that we do not allow. Please edit your content to remove the highlighted words below.
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...