Is there a way to sort a Revit schedule by project phase?

What I hope to make possible is the ability to sort both schedules and 3D visual models by phase while only having to change one parameter within the properties of each object.

Currently I can adjust both the 'phase', under phasing to allow me to filter my project visually and the likewise change the 'system', under identity to filter my schedules, but what I want is to be able to sort both by changing only one parameter, rather than 'phase' AND 'system'.

 

Any ideas?

 

Thanks

Link to comment
Share on other sites

  • 1 month later...

Why not create two schedules (or as many as you would like) for each phase you need, Then you need only change the phase to act visually and reference to the shedule as needed.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Unfortunately, your content contains terms that we do not allow. Please edit your content to remove the highlighted words below.
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...